Answer:
$35,000
Explanation:
Units started and completed means that out of the units completed and transferred, how many were started during the period. This figure is calculated in physical terms only. So there is no need to express any units in their equivalents.
So, this gives us an idea of how to calculate this :
Units started and completed = Units Completed and Transferred - Units in Beginning Work in Process
therefore,
Units started and completed = 40,000 units - 5,000 units = $35,000
Answer:
B) Direct materials price variance
Explanation:
Company uses sugar while producing a product, that means it is a direct material for the product, further provided that cost gets doubled of buying a unit of sugar, that is actual rate is now twice of earlier rate.
Therefore since only direct material price variance uses actual rate it will be affected.
Direct Material Price Variance = (Standard Price - Actual Price)
Actual quantity.
Else labor variance does not use direct material price, therefore option C) and option D) are invalid further direct material quantity variance uses standard rate and no actual rate is used.
Therefore correct option is
D) Direct Material Price Variance
Answer:
A - Set aside a portion of your income each month.
Hope This Helps