Capitalism because it was on the day they did it
Answer:
$9.2
0
Explanation:
The calculation of the Finishing Department is shown below:-
Plant - wide overhead rate = Total overhead ÷ Total machine hour
= ($470,000 + $737,900) ÷ ($470,000 + 133,950)
Plant wide overhead rate = $2 per machine hour
Machine hour for product = 4.2 + 0.4
= $4.6 machine hour
Applied overhead = Machine hour for product × Plant wide overhead rate
= $4.6 × $2
= $9.2
0
Answer:
$76,260
Explanation:
Calculation to determine the total period cost for the month under variable costing
Using this formula
Total Period cost = Variable selling and administrative cost + Fixed manufacturing overhead + Fixed selling and administrative cost
Let plug in the formula
Total Period cost = ($14 × 1,760) + $18,180 + $33,440
Total Period cost =$24,640+$18,180 + $33,440
Total Period cost =$76,260
Therefore the total period cost for the month under variable costing is $76,260
Answer: For residential rental property, the recovery period using GDS is 27.5 years. 2 If you use ADS, the recovery period for the same type of property is 30 years if it was placed in service after December 31, 2017, or 40 years if it was placed in service before that date.
Explanation: Is the good enough???
Answer:
Direct Material Price Variance = $300 Favorable
Explanation:
Direct Material Price Variance = (Standard Price - Actual Price)
Actual Quantity
Standard Price = $4 per pound
Actual Price =
= 
Since the actual price is less than the standard price the variance will be favorable as the amount paid for actual use is less then the estimated standard cost.
Thus, direct material price variance = ($4 - $3.8)
1,500
= $300 Favorable