1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
saw5 [17]
3 years ago
11

HELP ME PLEASE 40 POINTS AND BRIANLIESTS

Mathematics
2 answers:
shtirl [24]3 years ago
8 0

Answer:

2 to 3 seconds

Step-by-step explanation:

Constant is when the number doesn't change, and in this case, that is 2 to 3 seconds.

Mars2501 [29]3 years ago
4 0

Answer: i think it the 3rd one

Step-by-step explanation:

You might be interested in
It is easy! Help<br><br> Ill mark brainliest
Tamiku [17]

Answer:

a) 1

b) n² - n

c) 2n - 1

d) B, always odd

Step-by-step explanation:

8 0
3 years ago
A) Using the equation for average rate above, determine the cheetah's Please me forte
pychu [463]

Answer  The Mexican tribe where children of FOUR are fed mind-bending magic mushrooms by witchdoctors in 'surviving childhood' rituals

The hallucinogenic mushrooms grow in the hills of Mexico's Oaxaca state

Shamans give them to young children to celebrate their 'surviving infancy'

Alejandro Garces, three, will be fed the mushrooms by his parents in June

His family will chant to give thanks to pagan gods when the effects kick inStep-by-step explanation:

5 0
3 years ago
If Qr=58 and pq=13 find pr
Oksanka [162]

Answer:

PR=71

Step-by-step explanation:

visualize:

P                Q               R

O-------------O-------------O

       13               58

so if PQ + QR = PR, than 13+58=PR

13+58=71

PR=71

6 0
3 years ago
Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activitie
Lady bird [3.3K]

Answer:

Expected project duration  is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network.

Step-by-step explanation:

In project management, early start is the earliest moment at which a specific activity may start and early finish the earliest moment at which it can end. Early finish (es)  is computed as:

EF = ES + d

where d is the activity duration and ES early start

Early start is computed as

ES: Max (EF-1)

or the maximum early start of predecessory activities.

Once we have calculated these values in the network for each activity , the early finish of last activity corresponds to the expected project duration, the earliest time in which we may finish the project if there are no issues.

Max project duration is open question as we could have infinite delays or never finish the project. Time variance in project duration may only be estimated once we have actual execution times of our project.

Slack time and critical path are obtained after obtaining the ES and EF but this info alone is not sufficient. We require either the late start or the late finish of the activities to calculate slack, Zaero slack activities, those that cannot be delayed form critical path and can only be obtained after having ES. EF. LS and LF

5 0
3 years ago
What is the slope of the line that contains the points (-4,47) and (2,-16)?
EastWind [94]

The slope of the line is -10.5.

3 0
3 years ago
Other questions:
  • Three rock samples have masses of 74.05 grams, 9.72 grams, and 45.49 grams. A scientist estimates the tatal mass of the samples
    8·2 answers
  • A 950 gallon swimming pool is being drained. After seven hours, 500 gallons have been drained. If the rate of drainage continues
    12·1 answer
  • I need help with number 1 please show work
    9·1 answer
  • The Cowboys have won 3 out of 10 games. What<br> percent of the total games have the Cowboys won?
    10·1 answer
  • What is the answer to this I need help . multiply 3 ones by 2
    10·2 answers
  • I need help with number 9, please. I had made a mistake on my previous question
    15·1 answer
  • In a ballistic pendulum experiment, projectile 1 results in a max height,h, of the pendulum equal to 2.6cm. A second projectile
    6·1 answer
  • Hii! please help asap. i’ll give brainliest
    15·2 answers
  • Find the critical value ta/2 needed to construct a confidence interval of the given level with the given sample size. Round the
    12·1 answer
  • Help!!!!!!!!!!!!!!!!
    14·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!