My bests answer I got was a<3
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
83/13 or 6.3846
Step-by-step explanation:
i subsituted for x and used a calculator
Answer:
option c is the correct answer
Students with D's / total students : 3 / (7 + 9 + 11 + 3 + 2) =
3 / 32 = 0.0937...to turn to a percent, multiply by 100 = 9.375....rounded =
9.4% <== ur probability