1.72 because rocks 1 and 2 add up to 44.58 46.3-44.58=1.72
The partial variation is A
Choice 2222222222222222222222222222222
Answer:
240 hours
Step-by-step explanation:
One person hour is a unit indicating the rate at which one person is working on the project .
The company estimates that it will take 2880 person- hours to complete the job
So let's determine how many hours it will take 12 workers to complete same job
The rate = 2880 person/hour
12 persons or workers =( 2880 person/hour)/12 persons
12 persons or workers = 2880/12
12 persons or workers=240 hours
It will take 12 workers 240 person hour to finish the project.
Thank you
Answer:
Paint is measured in gallons
Step-by-step explanation: