Answer:
It explicitly incorporates uncertainty in one or more input variables.
Explanation:
In simulation analysis we perform 1000's of calculations assigning risk of uncertainty to multiple input variables, as with increased data set the variable tend to increase.
This technique is generally used, for project management and further, decision making in many streams.
Under this probability of different results in the form of outcomes are evaluated.
Therefore, the correct statement is b.
Answer: 12.5%
Explanation:
Given the following :
Beta (B) = 1.3
Marginal tax rate = 34%
Risk free interest rate = 6%
Market rate of return = 11%
The cost of equity is calculated using the relation:
Risk free rate of return + Beta(market rate of return - risk free rate of return)
Cost of equity = 6% + 1.3(11% - 6%)
Cost of equity = 6% + 1.3(5%)
Cost of equity = 6% + 6.5%
Cost of equity = 12.5%
Therefore, the firm's cost of internal equity is 12.5%
Answer:
44.44%
Explanation:
Profit is obtained by subtracting cost from revenue.
I,e.,
Profit = revenue - cost.
In this case,
Profit = $135,000 - $75,000
Profit = $60,000
As a percentage of revenue
= $60,000/ $135,000 x 100
= 0.44444 x 100
= 44.44 %
Answer: (A) Budget
Explanation:
Budget is one of the type of financial plan that is create according to our requirement and also budget.
A budget is one of the type of document that is used for describe the detailed plan in the future and it is usually expressed into the quantitative terms.
The main objective of the budget is to creating a proper plan based on the expenses, revenue, liabilities and the cost in an organization and it also helps in balancing our expenses with the income.
Therefore, Budget is the correct answer.