Answer:
d. It determines the critical path for the completion of a series of interrelated activities.
Explanation:
The Critical Path method is a method to lay out the different steps or interrelated activities of a project, in a graphical manner, that shows the interrelations, the time each activity takes to complete, the different alternatives or paths for project completion, and the total completion time for the project.
It also shows the amount of time a delay in one of the activities would delay the project as a whole.
Answer:
28.63%
Explanation:
The computation of the cost of preferred stock is shown below:
Cost of the preferred stock = Dividend ÷ Price of the stock
where,
Dividend is
= $1,000 × $15%
= $150
And, the price of the stock is
= Market value of the stock - flotation cost
= $576 - $52
= $524
So, the cost of preferred stock is
= $150 ÷ $524
= 28.63%
We ignored the marginal tax rate i.e 40%
Answer:
Explanation:
first will need to calculate the Fv future value of this CD
Fv = Pv ( 1 + R )^n n = 4 /12 = 0.333333, r, rate = 4.5/100 = 0.045
Fv = $ 630000 ( 1+ 0.045)^0.33333 = $ 639311.69
a) the current value at 5 % Pv = Fv / ( 1+r)ⁿ
Pv = $ 639311.69 / ( 1.05)^0.3333 = $ 628998.41
b) the current price at 4.25% = $ 639311.69 / ( 1.0425)^0.3333 = $ 630503.20
Answer:
B. $ 12 comma 600 comma 000
Explanation:
15,000 units x $700 cost per unit = 10,500,000 total cost
markup policy for the firm: 20% of total cost
the sales price will be the total cost for the order plus a 20% of that cost as a gross profit margin.
sales price = cost x (1 + 20%)
sales price = total cost x 1.20
sales price = 10,500,000 x 1.2 = 12,600,000