Answer:
2.719 minutes
Step-by-step explanation:
Step 1 :
We have to consider using the M/G/I /GD /∞/∞ Queuing system with the rate of arrival λ and the rate of service μ.
Since average of 40 cars arrive every hour at the painting facility, it follows that:
Arrival rate λ = 40cars /hour
= 40/60 cars/hour
=2/3 cars/hour
More, we were told that 95% of the cars require 1 minute to paint, 5% must be painted twice and require 2.5 minutes to paint, therefore, the average time to paint a car is given by
95/100x1 + 5/100 x 2.5 = 19/20 + 1/8 = 43/40min
It follows that:
Service rates μ = 40/43cars/min
None of the answers are correct because it’s definitely not “Given” because x=20 is like an answer. It’s also not “Distributive Property”, “subtraction Property”, and or “Additional Property” b/c there’s nothing that can be distributed, subtract or add. It’s just an answer.
Answer:
Step-by-step explanation:
Sum of the angles of a triangle is ALWAYS 180°.
2x+3x+5x = 180°
10x = 180°
x = 18°
2x = 36°
3x = 54°
5x = 90°
The angles are 36°, 54°, and 90°