<span><span> The purpose of the analysis is not sufficiently clear, so analysts produce data that doesn’t shed any light on what act</span></span>
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Answer:
yes
Explanation:
the constitution does set down the rights of the people like right to freedom and right to equality
When all four elements of clarification, culture, compliance and connection are effectively addressed through a strategic onboarding system, the organization will be considered successful onboarding.
<h3>What is the successful onboarding?</h3>
A successful onboarding program is most expected to include clarification, compliance, culture, and connection and follow-ups, relying on the size and needs of any company. This is also called as the 4 C's of the onboarding.
Therefore, It all start out in the present moment, a new employee accepts the position.
Learn more about the successful onboarding, refer to:
brainly.com/question/10370903
#SPJ1