Answer:
D) planning master scheduling, material requirements planning, capacity requirements planning, detailed scheduling
Explanation:
The sequence of operational planning and control tasks that follow sales and operations planning is planning master scheduling, material requirements planning, capacity requirements planning, detailed scheduling.
Sales and operations planning (S&OP ) is a monthly integrated business management process that enables the executive management team to continually achieve objectives such as focus, control inventory costs, alignment and improve service levels of the organization.
The capital projects fund account for the 10 percent retainage as (B) II only.
<h3>
What is retainage?</h3>
- Retainage is a percentage of the agreed-upon contract price withheld until the work is substantially completed to ensure that the contractor or subcontractor will fulfill its responsibilities and complete a construction project.
- Retention is money kept back by one party in a contract as security for unfinished or defective work.
- Assume the contract is worth $20,000 and you're submitting a paid app after finishing 25% of the work.
- So you earned $5,000 during the pay period, but retainage is 5%. The current progress payment has been reduced by $250.
- As a result, the "Amount Due for this Request" will be $4,750.
So, in the given situation the capital projects fund account for the 10 percent retainage as (II) the credit for $400,000 to Contracts Payable-Retained Percentage, that is (B) II only.
Therefore, the capital projects fund account for the 10 percent retainage as (B) II only.
Know more about retainage here:
brainly.com/question/24101126
#SPJ4
The correct question is given below:
The capital projects fund of Hood River completed the construction of an addition to its city hall at a cost of $4,000,000. The city council approved payment of the amount due to the general contractor, less a 10 percent retainage. How should the capital projects fund account for the 10 percent retainage?
I. As a credit of $400,000 to Deferred Revenue-Retained Percentage
II. As the credit for $400,000 to Contracts Payable-Retained Percentage.
A. I only
B. II only
C. Either I or II
D. Neither I nor II
Answer:
Relative Frequency = Observed value for each cell / Total frequency * 100
Cause Relative Frequency
Pilot Error 619
Other human error 85
Weather 574
Mechanical problems 566
Sabotage 524
Total 2368
The total frequency is 2368
The calculation of the relative frequency distribution is
Cause Relative Frequency Result
Pilot Error 619/2368 * 100 26.14%
Other human error 85/2368 * 100 3.59%
Weather 574/2368 * 100 24.24%
Mechanical problems 566/2368 * 100 23.90%
Sabotage 524/2368 * 100 <u>22.13%</u>
Total 100%
Conclusion: The most serious threat to aviation safety is the Pilot error as it has the highest frequency. Pilot need to be more equipped with understanding and knowledge of how to deal with unexpected event i.e. turbulence, engine failure among others..
its all da same because it just a company
Answer:
the days payable outstanding is 91.25 days
Explanation:
The computation of the days payable outstanding is shown below:
Days' payable outstanding is
= (Accounts Payable ÷ Cost of goods sold) × total number of days in a year
= ($25,000 ÷ $100,00) × 365 days
= 91.25 days
We simply applied the above formula so that the correct value could come
And, the same is to be considered
Hence, the days payable outstanding is 91.25 days