Answer:
1
Step-by-step explanation:

Remember that 
Plug it in:



Answer:
a) 86%
b) 2nd unit = 82 hs.
3rd unit = 75 hs
c) 100th unit = 36 hs
Step-by-step explanation:
We can model the learning curve for manufacturing the units as:

where t is the time for the Xth unit, and a and b are parameters that we will calculate from the data,
We know that t(1)=95. Then, we have:

And we know that the fourth unit (X=4) take 71 hours to be completed (t(4)=71). Then, we can calculate the other parameter as:

We have the model for the learning curve:

The learning rate percentage is calculated from the b parameter:

The learning rate percentage is 86%.
b) The most likely times required for the 2nd and 3rd units are calculated with the model:

c) If we use the model to calculate the time required for the 100th unit, we have:

Answer: (-2, 4)
Step-by-step explanation: The right coordinate for point B with 7 units as distance is (-2,4). To arrive at the answer, the distance formula is used. The solution for the problem is:
7= √[(-2-5)² + (4-4)²)
The halfway point is 24
• First, add the two numbers: 32 + 16 = 48
• Second, divide the total by 2: 48/2 = 24