Answer:
A
Explanation:
I don't have a explanation
As per the given scenario, the interpersonal skill that should be used is negotiating effectively.
<h3>Who is a project manager?</h3>
A project manager refers to the person who is in overall charge of the planning and execution of a particular project.
As a project manager, the project is on number one priority. The interpersonal skill that is mainly used in this scenario is negotiating effectively.
Learn more about project manager here:
brainly.com/question/15610382
#SPJ1
Answer:
$6 per unit
Explanation:
using the weighted average method:
units completed 92,000 x 100% (both materials and conversion)
ending work in progress 24,000
- materials 90% completed = 21,600
- conversion 40% completed = 9,600
equivalent unit conversion costs = total conversion costs / total equivalent units of conversion
- total conversion costs = $20,320 + $15,240 + $$182,880 + $391,160 = $609,600
- total equivalent units of conversion = 92,000 + 9,600 = 101,600
equivalent unit conversion costs = $609,600 / 101,600 units = $6 per unit
Answer: $880.57
Explanation:
Assuming Par value of bond is $1,000.
Value of bond = (Coupon * Present value interest factor of annuity, no. years, required return) + Par Value/ (1 + required return)^ no. of years
Coupon = 5% * 1,000 = $50
Value of bond = (50 * 5.9713) + 1,000 / (1 + 7%)⁸
= 298.565 + 582
= $880.57
Answer:
The inventory TO is 3.6875
Explanation:

where:

Considering there is not sufficient information to calculate the begining inventory <u>we are going to work only with the ending inventory </u>so:

The inventory TO is 3.6875 This means the company sales their inventory almost 4 times per year.