The excel function for monthly payments is =PMT()
The excel function for cumulative total interest is =CUMIPMT()
Answer:
NPV = $28020.99
so he accept the this project as NPV value is positive
Explanation:
given data
CF 0 = $80000
CF 1 = $40000
CF 2 = $40000
CF 3 = $30000
CF 4 = $30000
discount rate r = 12%
solution
we get here Net present value (NPV) of the project that is total sum of the current value of all flow that is express as
NPV =
...........................1
put here value and we get
NPV =
solve it we get
NPV = - 80000 + 35714.29 + 31887.76 + 21353.41 + 19065.54
NPV = $28020.99
so he accept the this project as NPV value is positive
Answer:
The answer is (A)
<em>WAS</em><em> </em><em>THIS</em><em> </em><em>ANSWER</em><em> </em><em>HELPFUL</em><em>?</em><em> </em>
<em>MARK</em><em> </em><em>ME</em><em> </em><em>AS</em><em> </em><em>A</em><em> </em><em>BRAINLIEST</em>
Answer:
b. $200 loss is the correct option
Explanation:
=100*(105-87)+(MAX(105-105,0)-20)*100
=-200
Answer:
The correct answer is e. All of these choices are correct.
Explanation:
The efficient execution of the strategy depends to a large extent on competent personnel, more adequate competencies and competitive capacities, and an effective organization. Therefore, developing a capable organization is always a priority of strategy implementation.
There are three types of organizational development that are of utmost importance.:
- Select capable people for key positions.
- Ensure that the organization possesses the core skills, competencies, administrative talents, technical knowledge, competitive capabilities, and resource strengths it needs.
- Organize business processes, value chain activities and decision making in a way that leads to successful execution of the strategy.