Answer:
The coupon rate will be 6.6415%.
Explanation:
By using the financial calculator, the I/Y will be computed:
Where
PMT = 7/2 % × 1,000
= $35
PV = -$1,035
FV = 1,000
N = 16 × 2
= 32
It is semiannually, so the number of years got doubled.
Then press CPT and I/Y
I/Y = 3.3207
In order to compute the coupon rate, again financial calculator will be used:
PV = -$1,000
FV = $1,000
N = 32
I/Y = 3.3207
Then Press CPT and PMT
PMT = 33.2075
Coupon rate = PMT/ FV × 100
= 33.2705/ 1,000 × 100
= 3.32075%
The coupon rate will also be double:
= 3.32075% × 2
= 6.6415%
This is the annual rate.
A) exit because she leaves the unfavorable situation
Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.
Answer:
Annual repayment under option(i) is $1490
Annual repayment under option (ii) is $2189
Therefore option A is correct
Explanation:
Immediate repayment
Loan amount $10,000
Repayment period 10 years
Interest rate 8%
Let the annual repayment be X
:10000=X*(1/0.08)*(1-(1/(1.08)^10))
1/0.08 = 12.5
1-(1/(1.08)^10 = 0.536806512
12.5*0.536806512
=6.710081399
10000=X*6.710081
X = $1,490.29
5 years grace period
let P be accummulated loan value after 5 year
P=10000*(1.08)^5 =14693.28077
Let annual repayment be Q
14693.28=Q*(1/0.08)*(1-(1/(1.08)^10))
1/0.08 = 12.5
1-(1/(1.08)^10 = 0.536806512
12.5*0.536806512 =6.710081399
14693.28=Q*6.710081
Q 2189.73