a. Determine the standard cost per unit for direct materials and direct labor.
standard direct labor rate = $20 x 30/60 minutes = $10 per faucet
standard direct materials rate = $1.80 x 2.5 lbs = $4.50 per faucet
b. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance.
direct materials price variance = (actual price x actual quantity) - (standard price x actual quantity) = ($1.95 x 13,000) - ($1.80 x 12,500) = $25,350 - $22,500 = $2,850 UNFAVORABLE
direct materials quantity variance = (standard price x actual quantity) -(standard price x standard quantity) = ($1.80 x 13,000) - ($1.80 x 12,500) = $23,400 - $22,500 = $900 UNFAVORABLE
total direct materials variance = direct materials price variance + direct materials quantity variance = $2,850 + $900 = $3,750 UNFAVORABLE
Answer:
Equilibrium price will DECREASE and equilibrium quantity will INCREASE
Explanation:
Answer:
Correct answer is D. All future costs, both variable and fixed
Explanation:
In target costing, all future costs both variable and fixed costs are relevant. This is for us to clearly determine the desired profit that the company wants to attain. The process of costing is to determine all future costs that the company will possibly incur in the production and add it to the desired profit margin to know the unit sales price of the product.
It has been estimated that there are over 300 varieties of psychopathology. These have been divided into eleven major classes.
Answer:
independent, chain are the answer
Explanation: