Answer: 2.79 hours. 
Step-by-step explanation:
Given that the function for the learning process is T(x) = 2 + 0.3 1 x , where T(x) is the time, in hours, required to produce the xth unit
To calculate the time for the new worker to produce 10 units, substitute 10 for x in the equation above. 
T(x) = 2 + 0.31 (10)
T(x) = 2 + 3.1
T(x) = 5.1 hours 
To calculate the time for the new worker to produce 19 units, substitute 19 for x in the equation above. 
T(x) = 2 + 0.31(19)
T(x) = 2 + 5.89
T(x) = 7.89 hours 
The time required for a new worker to produce units 10 through 19 will be 
7.89 - 5.1 = 2.79 hours
 
        
             
        
        
        
Answer:
Step-by-step explanation:
-7x + 12 + (-8x + 48) = 180
-15x + 60 = 180
-15x = 120
x = -8
m<BDC= -7(-8)+ 12 = 56 + 12 = 68
m<CBA = -8(-8)+48 = 64+48 = 112
 
        
                    
             
        
        
        
There are so many types of angles, let's see what we've got here!
--(5x - 17) and 48 are alternate interior angles, which means that they are congruent.
--(5x - 17) and y are supplementary angles.
--48 and y are same-side interior angles, which means that they are also supplementary.
Let's solve for x first.
5x - 17 = 48
5x = 65
x = 13
Now, let's solve for y.
48 + y = 180
y = 132
Hope this helps!! :)
 
        
             
        
        
        
Answer:
For #2: It's C. 17 nickels and 15 quarters. 
Step-by-step explanation:
17*5= 85
15*25= 375
375+85= 460
add in the decimal:
17* 5 cents= $.85
15* 25 cents= $3.75
$3.75+ $.85= $4.60
 
        
             
        
        
        
3,3,2 these are the primes of 18