Answer:
Identify the sequence of tasks that take the longest to complete
Explanation:
Program Evaluation and Review Technique (PERT) is a project management tool that is used to manage potential contingencies in the process of executing a project. It is used to schedule ,organize and coordinate tasks in a project.
Determining the critical path on a PERT network lists out the time required for different tasks to be completed and as a result , the sequence of tasks that require the longest time are identified.
Answer:
A silent partner
Explanation:
A silent partner is a partner whose liability is limited to the amount invested in the project. Also, a limited partner hardly takes part in the day to day running of the business.
I hope my answer helps you
The correct answer is that the price elasticity of demand is elastic.
Price elasticity occurs when a change in price results in a change in demand. In this example, a 20 percent increase in the price of the drinks resulted in a 25 percent decrease in the demand for the product. Because the price increase resulted in a demand decrease the price is elastic.
Answer:
Businesses in free enterprise systems compete with each other to produce better products at better prices. Competition leads to innovation, new ideas and a more competitive market. Competiting allows businesses to control themselves and their ideas in an <em>efficent manner. </em>
<em>However, competition in the free enterprise systmem leads to lower wages and income.</em> It leads to the best product at the lowest price. It leads to a variety of products available to the consumer.
<u>if you liked my answer please mark me as brainliest !! thanks <3 !!</u>