Answer:
Step-by-step explanation:
x=−10, y=−3
x=10, y=7
y=7,x=10
y=−3,x=−10
Answer:
z= 104
y=76
x=76
Step-by-step explanation:
z+76= 180. solve for z
z=x
y=76
Answer:
A tree with a height of 6.2 ft is 3 standard deviations above the mean
Step-by-step explanation:
⇒
statement: A tree with a height of 5.4 ft is 1 standard deviation below the mean(FALSE)
an X value is found Z standard deviations from the mean mu if:

In this case we have: 

We have four different values of X and we must calculate the Z-score for each
For X =5.4\ ft

Therefore, A tree with a height of 5.4 ft is 1 standard deviation above the mean.
⇒
statement:A tree with a height of 4.6 ft is 1 standard deviation above the mean.
(FALSE)
For X =4.6 ft

Therefore, a tree with a height of 4.6 ft is 1 standard deviation below the mean
.
⇒
statement:A tree with a height of 5.8 ft is 2.5 standard deviations above the mean
(FALSE)
For X =5.8 ft

Therefore, a tree with a height of 5.8 ft is 2 standard deviation above the mean.
⇒
statement:A tree with a height of 6.2 ft is 3 standard deviations above the mean.
(TRUE)
For X =6.2\ ft

Therefore, a tree with a height of 6.2 ft is 3 standard deviations above the mean.
Using order of operations, the answer is 569.
Answer:
p(on schedule) ≈ 0.7755
Step-by-step explanation:
A suitable probability calculator can show you this answer.
_____
The z-values corresponding to the build time limits are ...
z = (37.5 -45)/6.75 ≈ -1.1111
z = (54 -45)/6.75 ≈ 1.3333
You can look these up in a suitable CDF table and find the difference between the values you find. That will be about ...
0.90879 -0.13326 = 0.77553
The probability assembly will stay on schedule is about 78%.