Answer: The correct answer is "C. Includes project documents".
Explanation: A project plan is a document that is normally used by managers to guide the execution and control of the project. In addition, it contains documents, assumptions of decision-making and all other information that helps expedite communication between the parties that make up the project and defines the scope, costs and objectives of the project.
Answer:
The way they're produced.
Explanation:
I can give an example. Henry Ford and his Model T. he wanted to increase the amount of cars his factory produced, and he wanted to make the production easier, and more affordable. His first step, was to make the production easier. He invented the conveyer belt, which stopped at each worker for an enough amount of time to let them complete their individual job. this's a great example
false
that is seditious conspiracy charges with 20 years of lawful jailing. because my friend called Pete Williams said.
Always agreeing with anyone above you
Not accepting ideas
Lack of communication, up and down and across
Keeping information inaccessible
Not understanding your customers
Staff don't participate in any decisions
No team work, everyone out for themselves
Little chance of advancement
No reward system
Not following their own policies
Inconsistency in products or service
Maybe that's enough, huh?
Answer:
7.29%
Explanation:
The computation of the current yield of the bond is shown below;
Current yield is
= (Par value × annual coupon rate) ÷ Selling price of the bond
= ($1,000 × 7.2%) ÷ $988.22
= $72 ÷ $988.22
= 7.29%
Hence, the bond current yield is 7.29%
This is to be computed by applying the above formula so that the current bond yield could arrive