Answer:
a. 95.4
b. UCL = 96.07
LCL = 94.73
c. Process is in control
Step-by-step explanation:
a. The computation of estimate mean is shown below:-

= 95.4
b. The computation of Upper Control Limit (UCL) and the Lower Control Limit (LCL) for the manufacturing process is shown below:-


= 95.4 + 0.67082
= 96.07


= 95.4 - 0.67082
= 94.73
c. The explanation is shown below:-
From the above calculation we can see that the sample lies between LCL AND UCL that is (94.73 ,96.07) ,
The Process is in control
Answer:
8x+5=133
8x=128
x=16
Step-by-step explanation:
16 books
Answer:
5.5% probability that a randomly selected person plays soccer
Step-by-step explanation:
A probability is the number of desired outcomes divided by the number of total outcomes.
Desired outcomes:
People surveyed who play soccer, so 
Total outcomes:
Total people surveyed, so 
What is the probability that a randomly selected person plays soccer?

5.5% probability that a randomly selected person plays soccer
By rewriting the given line, we can see that the slope is equal to -1/2 or -0.5
<h3>
How to get the slope of the given line?</h3>
Remember that a line is:
y = a*x + b
Where a is the slope and b is the y-intercept of the line, which is the point where the line intersects the y-axis.
Then, we can rewrite our equation:
x + 2y = 16
to:
2y = 16 - x
y = (16 - x)/2
y = (-1/2)*x + 8
Comparing with the general line equation, we can see that the slope is -1/2.