Answer: 14 weeks 5 days
Step-by-step explanation:
From the question, we are informed that Amir has 103 days to finish a project and that he works 7 days a week on the project.
The number of weeks and days that he has to finish the project will be:
= 103/7
= 14 5/7
= 14 weeks 5 days
Answer:
486
Step-by-step explanation:
for the 2nd term, add 5 to -9
for the 3rd, add 5 × 2 to -9
for the 4th, add 5 × 3 to -9
:
for the 100th, add 5 × (100 - 1) to -9
=> 5 × 99 + (-9)
=> 486
Step-by-step explanation:
here will take the earth's surface as 0.
hence,
the first hole that Sally dug is 5 feet below the surface making its integer -5
the second hole Sally dug was 8 feet below the surface making its integer -8
therefore, the roses are closest to the surface.
Ok. I’m not the smartest person. But, if I understand the question I have to divide 288 by 2. That would be 144.. but it seems too easy. Correct me if I’m wrong