3 years ago
14

Maritime Marine Company has total estimated factory overhead for the year of $986,800, divided into four activities: fabrication

, $386,400; assembly, $207,900; setup, $112,000; and inspection, $280,500. Maritime manufactures two types of boats: a speedboat and a bass boat. The activity-base usage quantities for each product by each activity are as follows:
Fabrication Assembly Setup Inspection

Speedboat 1,200 dlh 1,800 dlh 60 setups 600 inspections
Bass boat 1,800 1,200 100 200
3,000 dlh 3,000 dlh 160 setups 800 inspections

Required:
a. Determine the activity rates for each activity.
b. Determine the factory overhead cost per unit for each product, using activity-based costing.
Business
1 answer:
Hatshy [7]3 years ago
5 0

Answer:

Instructions are below.

Explanation:

Giving the following information:

Estimated costs:

fabrication= $386,400

assembly= $207,900

setup= $112,000

inspection= $280,500.

Fabrication Assembly Setup Inspection

Speedboat: 1,200 dlh 1,800 dlh 60 setups 600 inspections

Bass boat: 1,800 1,200 100 200

3,000 dlh 3,000 dlh 160 setups 800 inspections

First, we need to calculate the overhead rate for each activity:

Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

fabrication= 386,400/3,000= $128.8 per direct labor hour

assembly= 207,900/3,000= $69.3 per direct labor hour

setup= 112,000/160= $700 per setup

inspection= 280,500/800= $350.63 per inspection

Now, we can allocate overhead to each product:

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Speedboat= 1,200*128.8 + 1,800*69.3 + 60*700 + 600*350.63

Speedboat= $531,678

Bass boat= 1,800* 128.8 + 1,200*69.3 + 100*700 + 200*350.63

Bass boat= 455,126

You might be interested in
Cogswell cola purchased a machine for $237,500. The firm paid another $5,750 for delivery and installation. In addition the firm
Novay_Z [31]

Based on the cost of purchasing the machine and the delivery and installation fees, the initial outlay is $243,250

<h3>How much is the initial outlay?</h3>

This can be found as:

= Cost of purchasing machine + Installation and delivery cost

Solving gives:

= 237,500 + 5,750

= $243,250

Find out more on fixed asset capitalization at brainly.com/question/25355478

#SPJ1

3 0
2 years ago
B&amp;T Company's production costs for May are: direct labor, $16,000; indirect labor, $6,800; direct materials, $15,300; proper
schepotkina [342]

Answer:

B&T Company's factory overhead incurred for May is $8,890

Explanation:

Manufacturing overhead is all indirect costs incurred during the production process, includes indirect labor cost.

In B&T Company,

Factory overhead incurred for May = Indirect labor cost + property taxes on production facility cost + factory heat, lights and power cost + insurance on plant and equipment cost = $6,800 + $830 + $1,030 + $230 = $8,890

6 0
3 years ago
Widget Maker Manufacturing uses job costing. In​ May, material requisitions were $ 44,300 ​($ 39,700 of these were direct​ mater
Airida [17]

Answer:

Beginning Material = $11,500

Explanation:

given data

material requisitions = $44,300

direct​ materials = $39,700

raw material purchases = $58,100

end month balance raw materials inventory = $25,300

to find out

beginning raw materials inventory​ balance

solution

we know that Beginning Material is express as here

Beginning Material = Ending Material - Purchases + Requisitions ..............1

put here value in equation 1  we get

Beginning Material = Ending Material - Purchases + Requisitions

Beginning Material = $25,300 - $58,100 + $44,300

Beginning Material = $11,500

3 0
3 years ago
On January 1 st 2012, Everhart Corporation, a calendar year company issues $100,000, 5%, 5-year bonds dated January 1, 2012. The
Alborosie

Answer:

Interest expense 2894.7 debit

discount on Bonds Payable 394.7 credit

cash 2500 credit

Interest expense 2906.55 debit

discount on Bonds Payable 406.55 credit

interest payable  2500 credit

Explanation:

We have to solve for the 2013 year which is one year after the issuance ofthe bonds.

We solve for the bond issuance price and then, we construct the bonds schedule and take the numbers from period 3 and 4.

Issuance proceeds: present value fo the coupon payment and maturity at market rate:

C \times \frac{1-(1+r)^{-time} }{rate} = PV\\

C 2,500.000

time 10

rate 0.03

2500 \times \frac{1-(1+0.03)^{-10} }{0.03} = PV\\

PV $21,325.5071

\frac{Maturity}{(1 + rate)^{time} } = PV  

Maturity   100,000.00

time   10.00

rate  0.03

\frac{100000}{(1 + 0.03)^{10} } = PV  

PV   74,409.39

PV c $21,325.5071

PV m  $74,409.3915

Total $95,734.8986

Now we will calcautlethe interest expense by multiplying carrying value by the market value and sutract from the cash outlay to determinate the amortization on the bonds.

7 0
3 years ago
M6
lbvjy [14]

Answer:

45

Explanation:

8 0
3 years ago
Other questions:
  • A bank reconciliation revealed cash per the bank statement of $1,484, cash per company records of $1,681, bank charges of $11, d
    6·1 answer
  • Explain how and why governments may want to regulate the price setting of a natural monopoly.
    6·1 answer
  • Market size and growth rates in different countries can be influenced positively or negatively by A. population sizes, income le
    6·1 answer
  • Calculate the present value of an annuity immediate with 20 annual payments of 500 if the first payment of the annuity immediate
    8·1 answer
  • Between 1986 and 1998 the De Beers company controlled the world diamond market. De Beers and its affiliated association of produ
    9·1 answer
  • How to stop smoking<br><br> plz help<br> im spent £40 a day
    14·2 answers
  • Couurtney bought a shirt for $24. with a coupon for 25% off. what was the original price of the shirt before the discount
    15·1 answer
  • Given the rapid advancements in technology in developed countries and fast pace of globalization, it is not possible to bridge t
    9·1 answer
  • What are the opportunity offers by<br>vocational education?​
    5·1 answer
  • Amaya is a member of a new product design team. The team leader proposed a process that would get quick results, but Amaya was c
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!