Answer:
7 workers will be required
Explanation:
We will define actual time required to do a job
= Standard time required for producing each unit x Worker efficiency (%)/100
= 11.65 x 115/100
= 13.3975 minutes
Total available minutes in 4 days = 4 days x 8 hours/ day x 60 minutes / day = 1920 minutes
Therefore ,
Number of units which can be produced by 1 worker in 4 days = 1920 /13.3975
Number of units to be produced = 1000 units
Therefore,
Number of workers required
= Number of units to be produced / Number of units which can be produced by 1 worker in 4 days
= 1000 x ( 13.3975 /1920)
= 6.977 ( 7 rounded to nearest whole number )
Answer:
1. Rule out other explanations such as an error by the computer distributor.
Explanation:
The best and most appropriate action is to rule out explanation. There can be an error with the shipment or by computer distributor. Before suspecting Bill for the missing computer we need to seek explanation from him. The computer can either be loss or missed out when shipped. Bill should be asked to explain the missing inventory. The explanation from Bill can be a point for further investigation.
The perimeter is the total distance around the outside of a shape. In the case of a rectangle, opposite sides of the rectangle are equal. Here is a formula for finding the perimeter of a rectangle: P=2(l+w) or Perimeter = 2 × length + width