Answer:
The correct answer is letter "B": attention.
Explanation:
Attention is the mental activity by which individuals focus their attention on a given subject they are dealing with. By doing this, people leave behind any other situation around to concentrate only on the task they are given. This scenario takes place in complicated exercises that push people's knowledge to the limit or when the exercise is of interest or important for the individual.
Answer:
the bond's price elasticity = - 0.67
Explanation:
present bond value = $1100
previous bond value = $900
change in bond value = $1100 - $900 = $200
present bond percentage = 8%
previous bond percentage = 12%
% change in bond value = 8% - 12% = - 4%
Bond price elasticity = 
= 
= 
= - 0.67
Question: The question is incomplete. See the full question below and the answer.
You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):
Contractor Cost Time
A 100 20
B 80 25
C 79 28
D 82 26
The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)
Answer:
See the explanation for the answer and find attached of the graph.
Explanation:
So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.
Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.
So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.
Answer:
A sole proprietorship is established when an owner begins operating their business.
Explanation:
There are no separate licenses to obtain to form a sole proprietorship. The sole proprietorship will be maintained so long as the owner keeps doing business.
Answer: C. Top level managers may pursue their own interests over that of the company.
Explanation:
The scenario given in the question explains that top level managers may pursue their own interests over that of the company.
In the case of sole proprietorship or partnership business, the revenue generated by the firm or the profit made belongs to the owners. In the case of of a Corporation, this isn't the case as the revenue should be used for Shareholders benefits. Sometimes, there may be a conflict of interest which may then bring about a situation whereby the top level managers pursue their own interests over that of the company.
Hence, the correct option is C.