Answer:
Instructions are listed below.
Explanation:
Giving the following information:
Each unit of output requires 0.52 direct labor-hours. The direct labor rate is $9.00 per direct labor-hour. The production budget calls for producing 1,700 units in April and 1,600 units in May. The company is committed to paying its direct labor workforce for at least 960 hours a month.
We need to calculate the total number of hours required each month.
April:
Direct labor hours= 1,700 units* 0.52= 884 hours
Total cost= 960 hours*$9= $8,640
May:
Direct labor hours= 1,600 units* 0.52= 832 hours
Total cost= 960 hours*$9= $8,640
Answer:
Explanation:
A. The journal entries are shown below:
On September 12
Investment A/c - Bengals Inc A/c Dr $598,220 (42,730 × $14)
To Cash A/c $598,220
(Being the acquired investment including brokerage commission is recorded)
On December 31
Unrealized gain or loss on available-for-sale securities A/c Dr $85,460
To Valuation allowance for available-for-sale securities $85,460
(Being decline in share value is recorded)
The computation is shown below:
= 42,730 shares × ($14 per share - $12 per share)
= 42,730 shares × $2 per share
= $85,460
B. The unrealized gain or loss for available-for-sale investments is shown in the Stockholder equity section on the balance sheet. It is to be shown in the negative item in the equity section.
Answer:
e. The company will take on too many high-risk projects and reject too many low-risk projects.
Explanation:
By using the WACC for discounting purposes in case of the higher risk projects the net present value would be greater in such cases and also the high discount rate is applied. It is easily accepted but at the same time it also rise the organization risk
Therefore in the given case, the option e is correct and the same is to be considered
A, true. hope this helped you!!!