Answer:
amount of commission (load) Jan must pay is $1755
Explanation:
given data
investment = $39,000
charges commission (load) = 4.5 percent
to find out
Calculate the amount of commission (load) Jan must pay
solution
we get amount of commission will be here as
amount of commission = investment × charges commission % ......................1
put here value we will get
amount of commission = $39000 × 4.5%
amount of commission = $39000 × 0.045
amount of commission = $1755
so amount of commission (load) Jan must pay is $1755
Answer:
($23,000)
Explanation:
Cash flow from Investing Activities
Purchase of furniture ($ 8,000)
Proceeds from sale of Equipment $5,000
Investment in other companies ($20,000)
Net Cash used by Investing Activities ($23,000)
Notes :
Cash flow from Investing activities section of the cash flows statement shows the cash movement in acquisition of assets and sale of assets.
Answer:
$5100
Explanation:
The cost of the inventory in $25000 and the cost of shipping it to the consignee, $500.
The cost of marketing brochures an comissions are recognized as expense and do not affect inventory. If 80% of the inventory was sold, 20% remains, which will have a carrying value of $25,500 X 20% = $5100
Answer:
correct option is d. $4800 U
Explanation:
given data
product requiring = 3 direct labor hours
standard rate = $ 16 per direct labor hour
produced using = 8700 direct labor hours
actual payroll = $135720
to find out
labor quantity variance
solution
we get here labor quantity variance that is express as
Direct labor quantity variance = (standard hours worked for actual production - actual hour worked) × standard rate per direct labor hour ...................1
here standard hours worked for actual production will be as
standard hours worked = standard hours required per unit of production × actual units produced
standard hours worked = 3 × 2800
standard hours worked = 8400 hours but we have given actual work hour 8700 direct labor hours
so put all value is equation 1 we get
Direct labor quantity variance = ( 8400 - 8700 ) × $16
Direct labor quantity variance = $4800 unfavorable
so correct option is d. $4800 U