Nata [24]
3 years ago
7

After having a pool built in their backyard, the Harrisons have contracted to have a fence installed around the pool. They want

to use 300 ft of fencing, and they plan to attatch the fence to the house. The Back of the house is 90 ft long, but they have instructed the fencing co. To use whatever portion of the house will maximize the area of the rectangular enclosure.
Mathematics
1 answer:
artcher [175]3 years ago
3 0

Answer:

27000

Step-by-step explanation:

Just multiple 300 and 90

You might be interested in
The area of a triangle is 41 yd^2, with a base of 5 yards. What is the height, in yards?
Annette [7]

Answer:

I am pretty sure the answer would  be A.

8 0
3 years ago
5+r−2=9 what is da value of R?
Basile [38]

Answer:

r=9-5+2

r=6

Step-by-step explanation:

this is the correct answer

please mark me as brainlist

5 0
3 years ago
I need help ASAP PLEASE ASAP!!!
zysi [14]
The area is 10 just use a area calculator!
3 0
2 years ago
Read 2 more answers
An assembly line with 10 tasks needs be designed. The total time for all tasks is 16 minutes. If you need to produce 30 units/ho
Sindrei [870]

Answer: 8 minimum work stations is what would be needed.

Step-by-step explanation:

The cycle time is computed as the operating time daily divided by the scheduled output.

It is important to note that the daily capacity of the operation layout is the operating time divided by the cycle time.

Therefore,

If you need to produce 30units/hour.

The average cycle time is as follow:

The average cycle time is the average time between the completions of units.

60/30= 2 average cycle time

=16/2

=8

8 work stations is the minimum number that would be needed.

It is important to know that in an assembly line balancing, the minimum number of work station is the ratio of the sum of all tasks time to the cycle time.

5 0
3 years ago
Find the measure of the missing angles.
Sergio039 [100]

Answer:

d = 105° , e = 32° , f = 43°

Step-by-step explanation:

d and 105° are vertically opposite angles and are congruent , then

d = 105°

e and 32° are vertically opposite angles and are congruent , then

e = 32°

105° , e and f lie on a straight line and sum to 180° , that is

105° + e + f = 180°

105° + 32° + f = 180°

137° + f = 180° ( subtract 137° from both sides )

f = 43°

8 0
2 years ago
Read 2 more answers
Other questions:
  • Darelene has 3/4 lb. of almonds. She needs to share it equally among 6 freinds. How many will each freind be given ( please show
    11·1 answer
  • How many milliliters are in 30 liters? <br><br> 300<br> 3,000<br> 30,000<br> 300,000
    7·1 answer
  • 48x2 + 48xy2 + 12y4 =
    5·2 answers
  • Quadrilateral A’B’C’D’ is a dilation of quadrilateral ABCD about point P with a scale factor of 2 1/2 .
    15·2 answers
  • Summary of Arrow of Destiny
    14·1 answer
  • Please Help! 30 POINTS! Given the following three points, find by hand the quadratic function they represent. (−1,−8), (0,−1),(1
    14·1 answer
  • Find missing measure
    13·1 answer
  • In the trapezoid, what is the measure of 1?
    10·1 answer
  • How many 1/2 hours are in 1 hour
    6·1 answer
  • Solve for x.
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!