Given a 7 percent interest rate, compute the present value of payments made in years 1, 2, 3, and 4 of $1,350, $1,550, $1,550, a
igor_vitrenko [27]
Answer:
The present value of cash flows is $ 5,292.13
Explanation:
The present value is today's equivalence of the company's future cash flow discounted using the 7% interest rate as a discount rate.
Formula for pv of a cash flow=cash flow/(1+r)^n
r is the 7% interest rate
n is the relevant year each cash flow relates to
PV=$1,350/(1+7%)^1+$1550/(1+7%)^2+$1550/(1+7%)^3+$1850/(1+7%)^4=
$ 5,292.13
Answer:
B. index
Explanation:
New investors may want to consider to invest in index funds because they focus on a particular sector of the market or a particular type of bond, or indexes may follow and try to reciprocate the market for eg the. The purpose of an index fund is to copy and reciprocate the performance of a market index .
<span>Unified Communications is the term for the business trend that seeks to simplify and integrate all forms of communication. It's an evolving set of technologies that automate and unify through reduced latency, flow management, and elimination of device and media dependencies.</span>
Computer folders can also store other types of files, such as applications, archives, scripts, and libraries. All folders are subfolders, or subdirectories of the root directory.
Answer:
The NPV from opening the branch office is negative ( -$106668.08). Thus the branch office should not be opened.
Explanation:
The decision to open the branch office will be taken based on the NPV provided by opening of the branch office. If the NPV of a project is positive based on the required rate of return used as a discount rate fro cash flows, the investment is worth undertaking.
The net present value (NPV) for a project can be calculated as,
NPV = CF1 / (1+r) + CF2 / (1+r)² + ... + CFn / (1+r)^n - Initial Outlay
Where,
- r is the appropriate discount rate
- Initial Outlay is the Initial cost of the project
- CF represents cash flows from the project
As the required return is 16%, we will take this as the appropriate discount rate.
NPV = 45000 / (1+0.16) + 120000 / (1+0.16)² + 150000 / (1+0.16)³ +
150000 / (1+0.16)^4 + 150000 / (1+0.16)^5 - 485000
NPV = - $106668.08
As the NPV from project is negative at a required return of 16%, the project should not be under taken and the branch office should not be open.