Answer:
(a) 5
(b) $150 million
(c) 45 million
Explanation:
(a) Multiplier = 1 ÷ (1 - MPC
)
= 1 ÷ (1 - 0.8
)
= 1 ÷ 0.2
= 5 ⇒ the value of the simple multiplier is 5.
b) If the autonomous expenditure is increased by $30 million then the total output will increase by:
= $30 million × 5
= $150 million
c) If the Marginal propensity to import is 0.3 then the import will increase by:
= 150 × 0.3
= 45 million
Alice is willing to spend $30 on a pair of jeans, and has a coupon for $10 off she found online. She selects and purchases a $35 pair of jeans, pre-discount.
(Alice's consumer surplus, $5)
<span>Jeff finds some steaks for $16 for which he would have been willing to pay $20. The butcher notices the meat is near the expiration date and gives him an extra 75% off. </span>
(Jeff's consumer surplus, $16)
<span>Nicole has in her possession a hockey puck from the 2010 Winter Olympic Games and sells it on eBay. She will only sell the puck if the winning bid is greater than or equal to $500. After bidding closes, the last bid stands at $500. </span>
(Nicole's producer surplus, $0)
<span>Claire is trying to sell her used calculus textbook online. She asks for $150 or best offer and is willing to sell for anything over $100. She is able to sell it for $125. </span>
(Claire's producer surplus, $25)
<span>Roy is willing to pay $2.50 for a sports drink. He notices the price is $2.79 and chooses not to purchase a sports drink. (Roy's consumer surplus, $0)</span>
Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.
Answer:
Product
Explanation:
When a person is developing a plan, he must understand the product he is selling.
He can only develop an effective plan if he knows the complete dimensions of the product at hand. An incomplete understanding would lead to developing an ineffective plan that might create the wrong perception of it in the minds of the consumer and eventually effect the sales negatively or maybe engage the wrong market in the process.