Answer:
Jones may decide that the equity method would not be appropriate to account for the investment when Jones Company does not have significant influences over the management/operation of Sandridge Company.
Although an investors holding from 25% of investee is very much likely to have significant influences on the investee, this may not be true all over the times. For Jones, to prove that it does not have significant influences over Sandridge, there may be some following evidences:
+ Jones and Sandridge sign an agreement that Jones surrenders significant rights as a shareholder;
+ There is/are investor(s)/group(s) of investors who has more voting right than Jones and whose visionary/mission for Sandridge is opposite to Jones's.
+ Sandridge tries to reject Jones' influences on its management by seeking lawsuit or by successfully prevent representatives from Jones on its Board of Directors.
Explanation:
Answer: Chemicals such as insecticides, pesticides, and others must be kept away because they can contaminate food, and make it poisonous to anybody. Some can cause burns, vomiting, diarrhea, and in very large amounts, drowsiness or death. Chemical products may cause immediate health effects, such as skin or eye irritation or burns, or poisoning. There can also be longer-term health effects from chemicals.
Explanation:
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.