Answer:
Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
Answer:
Step-by-step explanation:
Check if the lengths of the sides follows the Pythagorean theorem.
9² + 12² ≟ 15²
81 + 144 ≟ 225
225 = 225
Triangle ABC is a right triangle.
Answer:
The answer is 7(8 + 3)
Step-by-step explanation:
7 x 8 = 56
7 x 3 = 21
pls mark brainlyest:)
Wen you deduct an amount from something
Answer:
Step-by-step explanation:
(-3/4)x + 9 = (-1/2)x + 8
9 - 8 = (-1/2)x + (3/4)x
1 = (1/4)x
x = 4
y = (-3/4)4 + 9
y = -3 + 9
y = 6