This is an example of "proximal goal".
Proximal objectives are best characterized as here and now and are instrumental in accomplishing distal objectives in which are long haul. The proximal objectives are the giving wellsprings of extra data in regards to exhibitions that isn't uncovered with a distal objective. It is basic that proximal objectives are more sensible to achieve the fulfillment on account of the time hole in getting the objectives. For a complex task, it would not bode well to have distal objectives set up in light of the fact that it at that point would set aside a long span of opportunity to close outcomes in a snappy way.
Answer:
yeah it will be worse than ever
Explanation:
in both cases
Answer:
Finish phase of the project life cycle.
Explanation:
The finish phase (or termination, or completion phase) of a project life cycle is basically when the project is completed and it is being delivered to the customer. Depending on the project, paperwork and documents are handed out to the customer, contracts with workers and suppliers are terminated. Everyone involved with the project must be notified about its completion and all obligations are paid for.
Answer:
$960
Explanation:
For computing the accumulated depreciation, first we have to compute the depreciation expense which is shown below:
= (Original cost - residual value) ÷ (useful life)
= ($9,600 - $0) ÷ (5 years)
= ($9,600) ÷ (5 years)
= $1,920
This is a full year depreciation but we have to find out for June 30,2017 i.e 6 months
= $1,920 ÷ 12 months × 6 months
= $960
The same is recorded as an accumulated depreciation