6

Problem 7.43 A chemical plant superintendent orders a process readjustment (namely shutdown and setting change) whenever the pH

of the final product falls below 6.92 or above 7.08. The sample pH is normally distributed with unknown mu and standard deviation 0.08. Determine the probability: (a) of readjusting (that is, the probability that the measurement is not in the acceptable region) when the process is operating as intended and mu
Mathematics
1 answer:
vaieri [72.5K]3 years ago
6 0

Complete Question

Problem 7.43

   A chemical plant superintendent orders a process readjustment (namely shutdown and setting change) whenever the pH of the final product falls below 6.92 or above 7.08. The sample pH is normally distributed with unknown mu and standard deviation 0.08. Determine the probability:

(a)

of readjusting (that is, the probability that the measurement is not in the acceptable region) when the process is operating as intended and \mu = 7.0 probability

(b)

of readjusting (that is, the probability that the measurement is not in the acceptable region) when the process is slightly off target, namely the mean pH is \mu = 7.02

Answer:

a

The value is  P(X < 6.92 or X > 7.08 ) =  0.26431  

b

The value  is P(X < 6.92 or X > 7.08 ) =  0.29344  

Step-by-step explanation:

From the question we are told that

  The mean is  \mu =  7.0

  The standard deviation is  \sigma  =  0.08

Considering question a

Generally the probability of readjusting when the process is operating as intended and mu  7.0 is mathematically represented as

       P(X < 6.92 or X > 7.08 ) =  P(X <  6.92  ) + P(X > 7.08)

=>    P(X < 6.92 or X > 7.08 ) =  P(\frac{X - \mu }{\sigma} < \frac{6.9 - 7}{0.08}  ) + P(\frac{X - \mu}{\sigma} >  \frac{7.08 - 7}{0.08} )

Generally

 \frac{X - \mu }{\sigma} = Z(The \  standardized \  value \ of \  X)

So

=> P(X < 6.92 or X > 7.08 ) =  P(Z < \frac{6.9 - 7}{0.08}  ) + P(Z >  \frac{7.08 - 7}{0.08} )    

=> P(X < 6.92 or X > 7.08 ) =  P(Z < -1.25) + P(Z >  1 )  

From the z table the probability of  (Z < -1.25) and  (Z >  1 ) is  

       P(Z < -1.25) =  0.10565

and

      P(Z >  1 ) = 0.15866

So

=> P(X < 6.92 or X > 7.08 ) =  0.10565 + 0.15866      

=> P(X < 6.92 or X > 7.08 ) =  0.26431      

Considering question b

Generally the probability of readjusting when the process is operating as intended and mu  7.02 is mathematically represented as

       P(X < 6.92 or X > 7.08 ) =  P(X <  6.92  ) + P(X > 7.08)

=>    P(X < 6.92 or X > 7.08 ) =  P(\frac{X - \mu }{\sigma} < \frac{6.9 - 7.02}{0.08}  ) + P(\frac{X - \mu}{\sigma} >  \frac{7.08 - 7.02}{0.08} )

Generally

 \frac{X - \mu }{\sigma} = Z(The \  standardized \  value \ of \  X)

So

=> P(X < 6.92 or X > 7.08 ) =  P(Z < \frac{6.9 - 7.02}{0.08}  ) + P(Z >  \frac{7.08 - 7.02}{0.08} )    

=> P(X < 6.92 or X > 7.08 ) =  P(Z < -1.5) + P(Z >  0.75 )  

From the z table the probability of  (Z < -1.5) and  (Z >  0.75 ) is  

       P(Z < -1.5) = 0.066807

and

      P(Z >  0.75 ) = 0.22663

So

=> P(X < 6.92 or X > 7.08 ) = 0.066807 + 0.22663      

=> P(X < 6.92 or X > 7.08 ) =  0.29344      

You might be interested in
9 of the 13 participants in a triathlon are men and the rest are women. What is the ratio of the number of women participating t
avanturin [10]

Answer:

123

Step-by-step explanation:

8 0
4 years ago
Target Costing
Lynna [10]

The target cost for Model J20 is $2000.

The required cost reduction is $30.

The total saving will be $30.3.

<h3>How to compute the cost?</h3>

The target cost will be:

= Sales price - (100% × Target cost)

= 400 - (100% × Y)

Y + Y = 400

2Y = 400

Y = 400/2 = 200

Target cost = $200

Therefore, the target cost is $200.

The required cost reduction will be:

= $230 - $200

= $30

The required cost reduction is $30.

The three engineering improvements together will be:

Direct labor reduction = 7.5

Additional inspection = 17

Injection molding = 5.8

Total savings = 30.3

The total savings is $30.3.

Learn more about cost on:

brainly.com/question/10705492

#SPJ1

6 0
2 years ago
If 1 egg boiled 3 minutes then6 eggs r boiled in..................min​
AleksAgata [21]

count by 3,

3 6 9 12 15 18

18 minutes for 6 eggs.

4 0
3 years ago
Read 2 more answers
Please help// geometry question.... geometry question pt.2
AlexFokin [52]

Answer:

a) E

b) line segment AB

Step-by-step explanation:

a) E

b) line segment AB (It's AB with the line over it - no arrowheads)

5 0
3 years ago
Find -2(3 - 8) + 3 (12 - 8)<br> What is the answer to this question?
goblinko [34]

Answer:

22

Step-by-step explanation:

3 0
3 years ago
Other questions:
  • In yurt a circular tent has a radius of 3 meters. What is the area of the floor of the yurt?
    5·1 answer
  • Pythagoras thereom ? help
    6·1 answer
  • Kenji buys 3 yard of fabric for 7.47 then he relizes that he need 2 more yard how much fbric will he need
    8·1 answer
  • I need help will give brainliest.
    10·1 answer
  • If a sample of 47 golfers is taken from a population of 183 golfers, the
    11·1 answer
  • Two consumers borrowed 10000 for five years bob has credit score of 650 and has an intrest rate of 11.5% while tyree has a credi
    6·1 answer
  • Timothy is filling fish bowls with pebbles at his fish store. He wants to have $\frac{1}{6}$ of a pound of pebbles in each fish
    6·1 answer
  • Find the values of x when y =1
    5·1 answer
  • Find the interest earned in three months if you deposit $500 in a savings
    15·1 answer
  • Help me on this new one please
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!