A. Compute labor productivity under each system. Use carts per worker per hour as the measure of labor productivity.
- old system = 70 carts / 6 workers = 11.67 carts per worker
- new system = 76 carts / 5 workers = 15.2 carts per worker
B. Compute the multifactor productivity under each system. Use carts per dollar cost (labor plus equipment) as the measure.
- old system = 70 carts / ($108 + $30) = 0.51 carts per dollar
- new system = 76 carts / ($90 + $41) = 0.58 carts per dollar
C. Comment on the changes in productivity according to the two measures.
- The new system is more productive and efficient since it uses less workers to produce a higher output. The additional costs of implementing the new system are lower than the cost of employing more workers.
Explanation:
Multi factor productivity = total output / (cost of wages + material cost + overhead cost)
Answer:
3. The work breakdown structure, the work packages, the budget and the schedule.
Explanation:
Supporting plans for the Project plan includes:
- Resource plans
- Communication Plans
- Risk management plans
- Quality plans
- Budget
- Procurement plans
- Scope
- Delivery schedule
Based on this we can say that option 3 is correct since it includes budget & schedules.
Answer:
A. Inelastic
B. a less than 10% increase in quantity supplied
Explanation:
A supply is inelastic when a percentage change in quantity supplied is less than percentage change in price.
A supply is inelastic if the price elascitiy is less than 1.
The answer is <u>decreases per unit.</u>
You're welcome & give me brainliest