Answer:
$30,000 unfavorable.
Explanation:
Calculation for what The direct labor efficiency variance for October was
Using this formula
Direct labor efficiency variance = (Standard hours for actual production - Actual hours) × Standard rate per hour
Let plug in the formula
Direct labor efficiency variance=(5,000 × 2 - $207,000 ÷ $18.00) × $20
Direct labor efficiency variance= (10000 - $11,500) × $20
Direct labor efficiency variance= $1,500 × $20
Direct labor efficiency variance= $30,000 unfavorable
Therefore The direct labor efficiency variance for October was $30,000 unfavorable
Answer:
Fixed costs= $2,600
Explanation:
Giving the following information:
January 6,400 $5,980
February 7,000 $6,400
March 4,000 $5,000
April 6,900 $6,330
May 9,000 $8,000
June 7,250 $6,575
<u>To calculate the fixed costs under the high-low method, we need to use the following formulas:</u>
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (8,000 - 5,000) / (9,000 - 4,000)
Variable cost per unit= $0.6 per unit
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 8,000 - (0.6*9,000)
Fixed costs= $2,600
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 5,000 - (0.6*4,000)
Fixed costs= $2,600
Answer:
A. True
Explanation:
Option A is correct because PIRs (planned independent requirements) are calculated based on actual and forecasted sales.
In PIR, the independent requirement for final goods is calculated by the sales and the activities /operation for material planning process.