Answer:
hello,
Step-by-step explanation:

Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
Sandwiches are $5.25 Bowls are $3.50
4x+5y=38.50
3x+9y=47.25
Answer:
6/5 or 1.2, they're the same value
Step-by-step explanation:
When it says "rate of change", it's really just asking for the slope. If you don't know what the slope is, essentially how much the y-value increases by whenever x increases by 1. This can be formally defined using the equation:
which is essentially
. The subtraction is finding the difference between the two numbers to see how much it's changed by. Btw the order doesn't matter, I could plug in (-3, -2) as (x2, y2) or I could plug it in as (x1, y1) as long as I make sure to input it in correctly. In this example I'll just say (-3, -2) = (x1, y1) and (2, 4) = (x2, y2). Plugging these values into the equation gives you:
that's the rate of change