Answer: Resource levelling
Explanation:
Resource levelling is a term used in project management defined and is defined as a technique used where there is adjustment in the start and finish dates based on limitation in resources with the aim of balancing the demand for resources using the available supply.
While performing activities in project planning, the manager will try to schedule some tasks simultaneously. Resource leveling can be used to balance the workload of the main resources during the duration of of the project usually at the expense of either the time, cost or scope.
B. To provide law and order
Answer:
11.61%
Explanation:
First, find the annual percentage return (APR) of this annuity. Using a financial calculator, input the following;
Recurring payment; PMT = -450
Future value ; FV = 27,000
Duration of investment ; N = 4*12 = 48 months
One -time present value; PV = 0
then compute interest rate; CPT I /Y= 0.92% (this is monthly rate)
APR = 0.92*12 = 11.035%
Effective Annual Rate (EAR) formula is as follows;
EAR = (1+
) ^m -1
EAR = 1+
)^12 -1
EAR = 1.1161 -1
EAR = 0.1161 or 11.61%
Answer:
$11,977
Explanation:
The difference between the balance of the total checks written and balance of the total checks presented for withdrawal gives the amount outstanding.
As such, amount of outstanding checks at the end of December is the net of the balance of the checks written in November and December and the balance of the checks presented in the same period.
This is
= $43300 + $59239 - $39630 - $50932
= $11,977
Answer:
D
Explanation:
when you lease a vehicle, your monthly payment will be calculated based on the vehicle's depreciation, or the change between its current value and its value at the end of the lease obviously plus interest and fees. .