Answer:
Possible transportation modes are discussed below in detail.
Explanation:
• Purchase Request: 12 - 25 days
• Process buy request abroad: 10 - 20 days.
• Manufacturing process: 60 days
• Transport from plant to port: 1-14 days
• Paperwork: 5 - 10 days
• Wait for the container: 1 - 7 days*
• Load compartments: 3 - 6 days
• Ship days: 28 days
• Custom clearance: 7 – 14 days
• Warehouse transportation: 1-3 days
Delivery time is around 136 minimum days and 191 maximum days. Likewise, the average delivery time is 163 days. Companies such as international trade specialist, trade logistics companies and Internet exchanges can help the company to reduce the delivery time by facilitating the trade channels. These intermediate channels can help to attain objectives in timely manner.
Answer:
1) assuming that the credit card company's payments are immediate (1 business day)
April 30,2015, net credit and debit card sales
Dr Cash 13,580
Cr Sales revenue 13,580
2) assuming that the credit card company's payments are immediate (1 business day)
April 30,2015, gross credit and debit card sales
Dr Cash 13,580
Dr Credit card fees 420
Cr Sales revenue 14,000
Answer:
The answer is <u>"$110 billion".</u>
Explanation:
Firms increase their investment by $11 billion
mpc = 0.9
gdp = ?
To find the gdp, first we have to find expenditure multiplier;
we will find that by using the formula;
expenditure multiplier = 1/(1-0.9) = 1/0.1 = 10
Now gdp = 10 x $11 billion
= $110 billion
Thus the <u>gdp is $110 billion.</u>
Light sources are laser lamps and leds