9 and 7/8 as a precent is 0.875 or 87%
Answer:
j=k+3 (j=jason k+kieth)
Step-by-step explanation:
he did thrhee more so it will be adding 3 to k
Answer:
5 4 3 2 1
Step-by-step explanation:
is this what ur asking
Answer:
that answer u put is correct and r u in K12 to lol
Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished