Total slack is calculated by the late finish minus early finish and the late start minus the early start
<h3>What is the total slack?</h3>
Total slack is simply the amount of time taken for a task to be delayed before the project finish date is delayed. It can be positive or negative.
It is calculated as the calculated as the value of the Late Finish minus the Early Finish field, and the Late Start minus the Early Start field.
Total slack = Late finish - early finish + late start - early start
Thus, the total slack is calculated by the late finish minus early finish and the late start minus the early start.
Learn more about slack time here:
brainly.com/question/13278483
#SPJ1
Answer:
0
Step-by-step explanation:
When put in between these lines || a negative number becomes positive and a positive number stays the same.
Answer:
x=2
Step-by-step explanation:
- add like terms (3x-9x= -6x, 7-3= 4)
- then move the constant to the right (-8+4=-12)
- finally divide it by 6 which gives you "x"
You can write the two equations x = 4y - 7 and x + y = 93; substitute the value of x into the other equation
(4y - 7) + y = 93; combine like terms
5y - 7 = 93; add 7 to both sides
5y = 100; divide both sides by 5
y = 20; substitute this value into the other equation
x + 20 = 93
x = 73
So the numbers are 20 and 73