Answer: b provides goods and services
Explanation: I m pretty positive this is the ans bye
Answer:
0.41
Explanation:
The computation of the weight of security Y in the minimum variance portfolio is shown below:-
Weight of security X = Standard deviation of security Y ÷ (Sum of the standard deviation of securities)
= 39% ÷ (39% + 27%)
= 39% ÷ 66%
= 59.01%
Weight of security Y = 1 - Weight of security X
= 1 - 59.01%
= 0.41
Answer:
$13,640 Unfavorable
Explanation:
Data provided
Actual hours = 2,600
Standard hours = 6.0
Standard variable overhead rate = $12.40
The computation of variable overhead efficiency variance is shown below:-
Variable overhead efficiency variance = (Actual hours - Standard hours) × Standard rate
= (2,600 - (250 × 6.0)) × $12.40
= (2,600 - 1,500) × $12.40
= 1,100 × $12.40
= $13,640 Unfavorable
Therefore for computing variable overhead efficiency variance we simply applied the above formula.
Answer: $150,000
Explanation:
The total cost of estimating and preparing the bid would normally fall between 1% and 2% of the total price of the bid.
It would therefore be best to use an average rate of these:
= ( 1 + 2) / 2
= 1.5%
The estimate will therefore be:
= 1.5% * 10,000,000
= $150,000
Complete/Correct Question:
When the company's dry goods deliveries were late for the third time, Melissa withheld payment from her supplier until it was back on schedule. This is an example of ________ power.
a. reward
b. referent
c. legitimate
d. coercive
e. Expertise
Answer:
D, coercive
Explanation:
Coercive power is the ability of a manager to be able to make an employee/subordinate follow orders by the use of force.
In the above question, Melissa withholds payment after her order of dry goods came in late a third time.
Withholding payment forced the supplier to return to the scheduled arrangement of delivery.
Cheers.