Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.
Answer:
Concurrent powers are powers enjoyed by both the state and federal government. These powers may be exercised simultaneously, in the same area, and among the same group of citizens. For instance, residents of most states are required to pay both federal and state taxes.
Answer:
e. Working to ensure that all variances are favorable.
Explanation:
the steps in effective management of variance analysis
Identifying questions and their explanations
Preparing standard cost performance reports
Taking corrective and strategic actions
Computing and analyzing variances
So the option is E.
Working to ensure that all variances are favorable.
Answer:
If A = { a , c , e } , B = { b , c , d ) and C = { a , c , d , f ) , find n ( A n B n C)