Jorge should provide feedback from all around the employee.
Answer:
the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively
Explanation:
The computation is shown below:
Cost assign to units transferred out is
= 40,200 units × $4 + 40,200 units × $10
= $160,800 + $402,000
= $562,800
And, the Cost assign to work in progress is
= 6,220 units × $4 + (6,220 units × 0.40) × $10
= $24,880 + $24,880
= $49,760
Hence, the costs to be assigned to the units transferred out and the units in ending work in process is $562,800 and $49,760 respectively
Increase in price leads to a decrease in supply.
<u>Answer:</u>
<em>Filmmakers want movie titles that are short, memorable, appealing to consumers, and without legal restriction to </em><u><em>appeal to multiple cultures
</em></u>
<em></em>
<u>Explanation:</u>
Many independent filmmakers are amazed at the measure of exertion and ability required to verify a fair conveyance understanding. With the emotional increment in an autonomous generation, it is evident that numerous movie producers have aced the skills expected to confirm the cash and hardware and deliver the film.
Subsequently, if the Filmmaker has skillfully made content into an engaging film, the movie producer might have the option to get a superior arrangement.
Answer:
1,390,718 shares
Explanation:
Amount to be raise = $72 million
Underwriters charges = 5%
Filling Fee = $700,000
After deducting the underwriters charges the amount remains 95% of the total value. The company needs to raise exact $72 million after all charges deducted so, will take this amount as 95% of the total and gross up this value to 100%.
Total Amount to be raised = Amount including the underwrites charge + Filling charge = ( $72,000,000 / 100% - 5% ) + $700,000 = $76,489,474
Share price = $55
Numbers of share = $76,489,474 / $55 = 1,390,718 shares