1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Elena-2011 [213]
3 years ago
6

That $3.00 app you wanted is on sale for 32% off. What will it cost now?

Mathematics
2 answers:
Diano4ka-milaya [45]3 years ago
3 0

Answer:

$2.04

Step-by-step explanation:

First, convert 32% in to a decimal.

.32

Then, multiply .32 by $3.

= $2.04

vodomira [7]3 years ago
3 0
<h2>Answer: approximately $2.04</h2>

You might be interested in
the area of a triangle is 124 square units. what would it's new area be if its base was half as long and its height was three ti
Montano1993 [528]
To solve this problem you must apply the proccedure shown below:

 1. You have that the formula for calculate the area of a triangle is:

 A=bh/2

 Where A is the area of the triangle, b is the base of the triangle and h is the height of the triangle.

 bh/2=124
 bh=124x2
 bh=248

 2. The problem asks for the new area of the triangle <span>if its base was half as long and its height was three times as long. Then, you have:

 Base=b/2
 Height=3h

 3. Therefore, when you substitute this into the formula for calculate the area of a triangle, you obtain:

 A'=bh/2

 (A' is the new area)

 A'=(b/2)(3)/2
 A'=3bh/4

 4. When you substitute bh=248 into </span>A'=3bh/4, you obtain:
<span>
 A'=186 units</span>²
<span>
 The answer is: </span>186 units²
3 0
3 years ago
Which number is greatest?
raketka [301]
A) =27.2
b) = 30.1
c) =31.2
d) =36.6

answer = D
8 0
4 years ago
Read 2 more answers
Three experts gave opinions on how long a task will take to finish. The estimates were 29, 10, and 12 days (in no particular ord
nirvana33 [79]

Answer:

15

Step-by-step explanation:

PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.

The formula is (O + 4M + P) ÷ 6

Where P is the most pessimistic = 29

M is the most likely = 12

O is the most optimistic = 10

Hence we have (10 + [4*12]+ 29) ÷ 6

= (10 + 48 + 29) ÷ 6

= 87÷6 = 14.5 ≈ 15

Rounded figure is equal to 15.

Hence the final answer to the question is 15

7 0
3 years ago
(HINT: your answer should be written as a rate.)<br> (Please Help) (ASAP)<br> POINT:20!!!
Anna71 [15]

Answer:

his average speed is 60 mph

Step-by-step explanation:

please mark brainliest, i need it for a new rank

<3

5 0
3 years ago
2 3/4 written as fraction greater than one
sladkih [1.3K]
2 3/4 = 11/4 <=== written as an improper fraction
3 0
3 years ago
Read 2 more answers
Other questions:
  • Which equation represents "the sum of eight times a number and seven is twice the number"? A) 8(7 + 2N) B) 8N = 7 + 2N. C) 7N +
    7·2 answers
  • Please helpp me thank you 20 pts
    10·1 answer
  • What numbers between 49 and 95 that are multiples of 2,3,and9
    15·1 answer
  • 8(-6a+2)+(-5)(-9a+2)
    15·2 answers
  • Match the correct theorem or postulate with the correct statement.
    15·1 answer
  • Which of the following is not something you should consider when evaluating an investment advisor? a. Their experience b. Whethe
    9·2 answers
  • What is .54 repeating as a fraction
    15·2 answers
  • Can someone help me please thank you:)
    15·1 answer
  • The probability that Sara wins a raffle is given by the expression n/n+3
    15·1 answer
  • Which polynomial are in standard form
    15·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!