Answer: Thus cost of concrete to pour the circular slab is <u><em>$ 94.25</em></u>
Step-by-step explanation:
Given
Diameter of circular slab, d=18 ft
Thickness of slab , t= 3 inches = 0.25 ft
Rate of concrete , R = $40.00 per cubic yard
Volume of the slab , ![V=\frac{\pi d^{2}t}{4}=\frac{\pi \times 18^{2}\times 0.25}{4} ft^{3}=63.6 ft^{3}](https://tex.z-dn.net/?f=V%3D%5Cfrac%7B%5Cpi%20d%5E%7B2%7Dt%7D%7B4%7D%3D%5Cfrac%7B%5Cpi%20%5Ctimes%2018%5E%7B2%7D%5Ctimes%200.25%7D%7B4%7D%20ft%5E%7B3%7D%3D63.6%20ft%5E%7B3%7D)
Now 1 cubic yard = 27 cubic feet
Therefore volume , ![V=63.6 ft^{3}=\frac{63.6}{27}yard^{3}=2.356yard^{3}](https://tex.z-dn.net/?f=V%3D63.6%20ft%5E%7B3%7D%3D%5Cfrac%7B63.6%7D%7B27%7Dyard%5E%7B3%7D%3D2.356yard%5E%7B3%7D)
=> cost of concrete , ![C=V\times R=\$ 2.356\times 40=\$ 94.25](https://tex.z-dn.net/?f=C%3DV%5Ctimes%20R%3D%5C%24%202.356%5Ctimes%2040%3D%5C%24%2094.25)
Thus cost of concrete to pour the circular slab is <u><em>$ 94.25</em></u>