Divides a line segment at the middle

Mathematics
1 answer:
bazaltina [42]3 years ago
8 0

Answer:  Midpoint

<u>Step-by-step explanation:</u>

Midpoint is the point that is equal distance from the endpoints.

You might be interested in
HELP IM STUCK !!!!!!!!!!
kramer

Answer: oof thats a hard one ummmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm

Step-by-step explanation:

3 0
3 years ago
When is the sun at the maximum height in the northen hemisphere????
Ugo [173]
Around December 21st in the northern hemisphere tell me if im wrong rate brainliest please
7 0
3 years ago
PLS HELP , I GOT ONLY ONE RIGHT AND THE REST ARE WRONG. I dont know what to do anymore pls help , its due todayyy plsjnn
Eva8 [605]
So, you already know that angle CBD is 68 degrees, and the complementary angle to angle CBD is angle CBA. These angles together make 180 degrees because segment DBA is a straight line consisting of angles CBD and CBA. 180-68(the angle you already know) is 112 degrees for angle CBA. Then you repeat this process to find the other angles
6 0
3 years ago
a worker A finishes a project on his own in 12 days. the worker completes the same work alone in 16 days. the two workers starte
ankoles [38]

Answer:

<em>Worker B needs 9 days to finish the rest of the work</em>

Step-by-step explanation:

<u>Proportions</u>

Worker A finishes a project on his own in 12 days and worker B does the same in 16 days.

Worker A does 1/12 of the project in one day and worker B does 1/16 of the project in one day. When working together, they do

\frac{1}{12}+\frac{1}{16}=\frac{7}{48}

After 3 days they have completed:

3*\frac{7}{48}=\frac{7}{16}

parts of the project, this means it still remains:

1-\frac{7}{16}=\frac{9}{16}

parts of the project and it is done by B alone. Since B does \frac{1}{16} per day, he now takes

\displaystyle \frac{\frac{9}{16}}{\frac{1}{16}}=9

days to complete the project.

Worker B needs 9 days to finish the rest of the work

4 0
3 years ago
What is the coefficient of the variable in the expression 6 - 4x - 8 + 2?
Lana71 [14]
The answer is -4. The coefficient of a variable is the numerical value directly in front of the variable.
4 0
3 years ago
Other questions:
  • Help pls I don’t get it
    11·2 answers
  • Which line best represents the line of best fit for this scatter plot?
    12·1 answer
  • What is 3819 divided by 19
    7·2 answers
  • Can someone please help
    7·1 answer
  • 5(x - 2) + 3 when x-7​
    5·1 answer
  • I am begging for help pls!!
    10·1 answer
  • What is 10.3% of 853.93km
    5·1 answer
  • If a parallelogram has a base of 9 units and a height of 2/3 units what is the area
    6·1 answer
  • 8/3 X 7/10 X 6/1 plz help me
    14·1 answer
  • Which of the following is a correct interpretation of the expression 3 - (-5)?
    6·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!