Answer:
Step-by-step explanation:
Area of one road = 700 x 10
7000 sq m
area of another road
= 300 x 10 = 3000sq m
Total area of road
= 7000 + 3000 - 10 x 10
= 9900 sq m
Area of park
= 700 x 300
= 210000 sq m
less area of road
= 210000 - 9900
= 200100 sq m
= 200100 / 10000 hectare
= 20.01 hectare.
Answer:
x: 3 = 23 -15
x = 8 x 3
x = 24
Step-by-step explanation:
Answer:
The correct answer is 10 days.
Step-by-step explanation:
To fill a trench, 5 men work for 6 hours a day for eight days.
Total work hours required is given by 5 × 6 × 8 = 240 hours.
The same work is supposed to be done by 3 men working 8 hours a day.
Let these three men need to work for x days.
Therefore total work hour these group of three men gave = 3 × 8 × x = 24x hours
Therefore the work hour of both the group of 5 men and 3 men should be equal.
⇒ 24x = 240
⇒ x = 10
Therefore the group of 3 men have to work for 10 days to fill the trench.
Area is equal to length times width, so 1.3x would represent the area. B is the answer.