Jim's path is the critical path on this activity graph.
Step-by-step explanation:
Critical Path:
Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.
In given case:
Path 1 Bill task's total duration= 6 days
Path 2 Jim's task's total duration= 17 days
Path 3 Betty task's total duration= 7 days
Path 4 Cynthia task's total duration= 14 days
Hence the longest path i.e. critical path is of Jim's activity path !
She’s incorrect I’m pretty sure u divide 20 and 60.
Well first we have to add 7/12 and 3/4 together which is 7/12+3/4=4/3. Now we have to reduce that to simplest form. Which would be 1 1/3 is 7/12+3/4 in simplest form!
Answer: 4, -1, [see if you can figure it out]
Step-by-step explanation:
Answer:
20.02%
Step-by-step explanation:
Formula : 
n = 1,2,3,4,5
Substitute the values in the formula :


Solving for IRR using calculator
IRR = 20.02
Hence the internal rate of return if the initial cost of the project is $275,000 is 20.02%