Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.
Answer:
The option B. The profits for common stock owners come before payment to employees, suppliers, government, and creditors. is the false statement.
Profit is any amount that is left after setting aside the cost and liabilities. It is financial gain which is represented by the difference between the amount that is spent and the amount that has been earned or gained. Whereas common stock is a kind of a common share holder equity which also considered to be a type of a security.
Answe and Explanation:
For banks and other financial institutions, the discrepancy between the short-term maturities of their deposits and the long-term maturities of their assets is referred to as _a maturity mismatch___________.
Answer:
A
Explanation:
Present Value relates to the amount that an investment would yield if the benefit were realized today. it is said to be the value of the future economic benefits an entity can generate