Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path
Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :
Probability
Thus the probability that the project will be completed in 38 weeks is 0.34.
Answer:
B. 10,000
Step-by-step explanation:
The volume of the jar is the product of its dimensions, so is ...
V = LWH = (7 cm)(7 cm)(6.5 cm) = 318.5 cm³
If we assume there are 10 m&ms in one cm³ (probably, the number is more like 3 or 4), then there could be about 3,200 m&ms in the jar. The nearest reasonable limit of those proposed is ...
10,000 . . . choice B
<span>Through any two points there exists exactly one...? Point, line or plane
Final answer: Line.</span>
So if the towns are 7cm apart and 1cm is equal to 500000, the. you need to times 500000 by 7 to get the actual distance, i hope this helps.